Sample shutdown schedule for heat exchanger cleaning and inspection work
The detail activity list for shell & tube heat exchanger cleaning and inspection work to be performed during shutdown period should be ready before develop schedule. The followings should be considered when you work out the activities, activity duration, manpower, tools and equipments requirement;
- Location of heat exchanger (To estimate scaffold Qty and lifting requirement)
- Pipe size
- Insulation type & thickness
- Shell & tube side flanges' size
- Tube bundle weight, length and tube size
- Design pressure on tube side & shell side
- Inspection requirements
Sample activities for heat exchanger cleaning and inspection work
Activities and work steps are very useful information. If you know the scope, steps and activities, schedule, resources and cost plan can be developed easily and monitored.
The followings are the activities for shell & tube heat exchanger (AES type)’s maintenance work required to perform cleaning work and inspection during shutdown.
The followings are the activities for shell & tube heat exchanger (AES type)’s maintenance work required to perform cleaning work and inspection during shutdown.
- Scaffold erection to access tube bundle pulling work & blinding & de-blinding work
- Remove pipe insulation for blinding work
- Line to be isolated, drain and purge the system ready to blinding
- Blinding work before pipe spools are removed
- Removal of channel head spools and shell side spools
- Removal of channel cover, channel head, shell cover and floating head
- Dis-assemble backing device