Changing of bar chart appearance is only made by the bar
dialog box and filters. It is the art of changing and customizing bar style,
bar color and filter list.
Three things you need to know about the bar chart in order
to be mastering in schedule layouts.
(1) Understand
how the existing bars works
(2) Know
how to customize existing bars
(3) Know
how to add the customized new bars
(1) Understand How The Existing Bars Works
Understanding how the existing bars works before changing
anything is essential. Below is a snapshot bar chart from one of the Primavera
P6 default layout.
To find out go to View under menu bar, select Bars…. Below are the snapshots
of Bars dialog window and their functions.
(1) Name Column where bar chart description
or bar labels are and also known as bar legend. It can be changed as you
desired.
(2) Time scale column where a drop down
list of the time scaled bars are. It cannot be changed or modified. For
instance, select Actual Bar from the dropdown list if you want to indicate the
actual works when project is progressed.
(3) Filter column where the desired filter
criteria are used.
(4) Preview Colum where the preview of bar
style and color is displayed when bar style format is changed.
(5) Bar Style where the bar style and color
can be changed as desired.
(6) Bar Setting where you can change the
appearance of bar by just changing “Grouping Band Setting and Bar Necking
Setting.
(7) Bar Labels where the customized bar
labels can be added. For instance, activity name can be displayed in left or
right side of the bar instead of displaying in the activity column.
In the above example, Fig-1, 2 and 3Actual Bar Timescale is selected for actual work (blue bar) and filter is set to Normal which means that any activity got actual progress will be displayed as blue bar. The first portion of activity will be displayed as blue when activity started and the completely became blue when the whole activity has been completed. See “New Activity 2 and 3” in Fig-1 and 2.
Remaining Bar Timescale is selected for the remaining works (green bar), and Normal and Non-critical activity filters are used. This means any non-critical remaining work will be displayed as green bar. Remaining portion of activity will be shown as green until activity completed. See “New Activity 3, 4 and 7” in Fig-1 and 2.
Remaining Bar Timescale is selected for the Critical Remaining work (red bar), and Normal and critical filters are used. This means any critical remaining work will be displayed as red until activity completed.
(2)
How to Customize The Existing Bars
If you know how existing bar works,
then customizing of existing bar is easy.
(1)
Select an existing bar
(2)
Go to bar style tag, and then change the bar
style format if you just want to make cosmetic changes.
(3)
Go to Bar Labels tag, add any content (user
define text, dates, float, etc.) that you want to show
(4)
Double click on the filter that you want to make
changes. Then, filter box will appear and select the desired filter. Remember
the select filter is one of the drivers of bar chart appearance.
(5)
Change the desired Timescale from the dropdown
list.
(6)
Select “Calendar
nonwork time” if you want to display non-working time.
(3)
How to Add The Customized New Bars
There
are endless options to add and display new bars depending on filter criteria,
bar style format.You might want to show the bar appearance based on the activity codes or user defines field criteria.
Suppose, user defined critical activities needs to be shown in your project.
a) Assign user define field code called “critical” for instance, in the selected activities. See fig-6. c) Change the desired bar style. In this example, red color is used. Remove the default critical bar. See Fig-7.
d) Select the “Remain Bar” Timescale.
Using this method, any activity can be highlighted differently from the crowed activities by means of graphical presentation.
Suppose activity bars need to be displayed according to activity code “Department” criteria (i.e. engineering, purchasing and construction department ) in addition to default bars. See Fig-8.
The department bars are displayed while Actual Work Bar, Remaining Work Bar and Critical Work Bar are being displayed.
a) Assign activity codes in the selected activities.
b) Add the new bars called “engineering”, “purchasing” and “construction department”. Then, change the desired bar style. Select the Current Bar Timescale so that it can be displayed all the time.
c) Add each filter to each bar. See Fig-9.
You might just want to change the bar’s appearance.
Suppose the progress bar and current bar needs to be shown according to stakeholders’ requirement, as shown in Fig-10
a) Remove the existing bars; Actual Work and Remaining Work
b) Add the new bars; Actual Progress and Current Work
c) Select Current Bar Timescale and set to all activity filters to the Current work bar.
d) Select Actual Bar Timescale and set to all activity filters to the Actual Progress bar. Set the bar format to narrow bar and middle position. See Fig-11
Finally,
you could create hundreds of layouts depending on the filters (activity codes,
user define fields) , bar style format color, bar style position and background
color and Time Scale selection.
Enjoy yourself.....
0 comments:
Post a Comment