Static Equipment-Column & Vessel, Shell & Tue Heat Exchangers Installation
Chipping & Padding --10%
Lifting & Rigging --60%
Alignment --10%
Inspection ---10%
Grouting ---10%
Package Equipment-Boiler Installation
Main Parts Installation (Main body, Economizer, Air Pre-heater, Stack)—55%
Stairway and ladder installation ----20%
Duct Installation (Including Damper) ----10%
Accessories (Fan, Silencer, Soot blower, Burner) Installation ----10%
Punch Items --- 5%
Package Equipment-Demineralization Plant
Chipping & Padding -----10%
Lifting & Rigging -----70%
Leveling & grouting ----10%
Alignment for rotating equipment-10%
Equipment access platforms/ladders
Assembly at site -----40%
Chipping & Padding -----10%
Lifting & Rigging -----70%
Leveling & grouting ----10%
Alignment for rotating equipment-10%
Assembly at site -----40%
Installation -----55%
Punch Item -----5%
Punch Item -----5%
Internal Tray Installation work for Reactor/Column/Drum/Vessel
Preparation----20%
Installation -----75%
Punch Item ----5%
Access platform installation -----20%
Tube Bundle Installation -----40%
Mechanical Part Installation -----30%
Final Alignment -----10%
Rotating Equipment-Pump/Compressor/Blower
Chipping & Padding -------5%
Lifting & Rigging ------40%
Leveling & Grouting ------15%
First Alignment -------30%
Final Alignment ------10%
From Suhail
ReplyDeleteExcellent information. Thanks for sharing.
K.Suhail
i wish to know how i can prepare a progress measurement table
ReplyDeleteHi,
ReplyDeleteProgress measurement table for mechanical equipment installation work can be found at How to Make Equipment Erection Progress Tracking System
HI
ReplyDeleteI need the WBS in detail for Boiler project
include
steel structure,piping,All equipment,
Thanks
Dear sir,
ReplyDeletePlease i want explanation, when doing your progress calculation and progress tracking, do you use Primavera in doing it? How do you do progress calculation using primavera and weighted factor ?
Thank you for your quick answers.