1) Understand the terms and confirm procurement work steps and weight factors for equipment work category
- Not Yet Start -0%
- Inquiry Issued to Bidders -10%
- Tender Evaluation and Client Approval -5%
- Purchase Order Placement to Vendor -10%
- Received Key Vendor Drawings -5%
- Approved Key Vendor Drawings -5%
- Fabrication (50%)
- Final Inspection Finished -5%
- Ex-Work -5%
- Delivery at Site -5%
- Not Yet Start -0%
- Inquiry Issued to Bidders -10%
- Tender Evaluation and Client Approval -5%
- Purchase Order Placement to Vendor -10%
- Fabrication (60%)
- Final Inspection Finished -5%
- Ex-Work -5%
- Delivery at Site -5%
Note: Weight factor (60%) of fabrication work step shall be prorated based on the duration between purchase order issued date and final inspection date. Procurement work step groupings and weight factor percentage may be different from your project team’s preferences.
3) Confirm planned procurement items (if possible, list down the each equipment number) and Planned Purchase order amount.
4) Secure the schedule of each procurement work step for each equipment or equipment group based on that particular requisition number.
5) Calculate the weighting for each requisition. Example for Pipe & fittings –CS; weighting = Planned PO amount of pipe & fitting-CS/ Total Project PO amount which is 15000/340,000 =0.04
Lets' make an assumption that the following are planned procurement items and planned purchase order amount.
- Pipe & fittings –CS [$15,000]
- Pipe & fittings-SS304 [$25,000]
- Pipe & fittings-Special items [$10,000]
- Shell & Tube Heat Exchangers (AHE-105, AHE-106) [$40,000]
- Columns & Vessel (ACD-140, ACD-145) [$28,000]
- Reactors (ACR-10, ACR-15) [$18,000]
- Pump AHP-230 A/B/C [$20,000]
- Pump ACP-450 A/B [$15,000]
- Compressor AHC-235 A/B [$ 27,000]
- Compressor EHC-215 A/B [$ 20,000]
- Control valves [$12,000]
- Instrument cables [$35,000]
- Safety Relief Valve (PRV) [$ 13,000]
- Orifice Plates and flanges [$7,000]
- Electrical Cables [$ 35,000]
- Pressure/Temperature Transmitters [$20,000]
6) Enter the data of step 1, 2, 3, 4 and 5 to get procurement progress calculation sheet as shown in table-1. Make sure you enter week ending date as the progress data will be shown weekly basic. For example; take the weekending date as 20 Feb 2011 when Plan PO placement date is 18 Feb 2011.
7) Calculate and enter weighted progress data for each requisition number as shown in table-2.
Example for Pipe & fittings-CS; Weighted Progress for Inquiry issued to Bidders = Procurement Work Step Weight factors (Materials)*Weighting which is 10% *0.04=0.44%
The total weighted progress should be 100% as work step weigh factor and weighting of each requisition are based on 100% (1). Check the formula again if you couldn't get 100%.
8) Calculate periodic plan and cumulative plan progress data using Table-1 Schedule data and Table-2 weighted progress data. For example; periodic progress data for week ending 10 Oct 2010 =SUMIF('Procurement Progress Sheet'!$F$7:$N$22,'Progress Curve'!C2,'Procurement Progress Sheet'!$F$27:$N$42)
9) And then, you should get the plan progress data as shown in Table-3.
9) And then, you should get the plan progress data as shown in Table-3.
How to update Actual Progress
- Work step codes are entered when the actual work steps are done. Once the work step code is entered the cum weight factor for work steps is updated automatically using H LOOK UP function.
- Individual % Complete is derived from the cum weight factor (work step) + weight factor (fabrication step) * fabrication progress. The actual fabrication progress data shall be received from vendor's progress report.
- Overall % Complete data is derived from the sum of each requisition's weightage * individual % complete.
Download a sample template for the procurement progress calculation sheet to learn more.
From Suhail.K,
ReplyDeleteNice and valuable information. Is it possible to upload excel spreadsheet that contains above information also?
Regards K.Suhail
@Anonymous
ReplyDeleteHi Suhail.K,
As requested, I have posted an excel template for procurement progress calculation procedure for easy reference. I hope you will enjoy it.
Hi!
Deleteperiodic progress data for week ending 10 Oct 2010 =SUMIF('Procurement Progress Sheet'!$F$7:$N$22,'Progress Curve'!C2,'Procurement Progress Sheet'!$F$27:$N$42)
Where can we find 'Progress Curve' please?
Hi,
DeleteTo find the Progress Curve,
Download the excel template from the link;
https://sites.google.com/site/toolbox4planning/home/progress-calculation/procurement-progress-calculation
Then, click on the progress data under Progress Curve tag where you can learn how the details progress data is obtained.
Worth Place for Planners....I love it
ReplyDeletePlease send me excel template for procurement progress calculation procedure phemmywuyi07@yahoo.com
ReplyDeleteHi Femi,
DeleteYou can download sample procurement progress calculation template here
Hi Min,
DeleteGreat piece of information, but unfortunately none of templates are available for download.
Would you mind forwarding them to sujith.pratap@gmail.com?
Many thanks,
Sujith
Dear Sujith,
DeleteGlad that information is useful. It is downloadable link. Click on the downward arrow button (blue color) link.Here is a simple instruction to download file from this site
Hello Min Oo, am new to this site. Concerning the procurement progress calculation, I don't know how you got table 3 above. The other steps were clear. Even after downloading the template i could not unravel the expression...=SUMIF('Procurement Progress Sheet'!$F$7:$N$22,'Progress Curve'!C2,'Procurement Progress Sheet'!$F$27:$N$42)
ReplyDeleteHI Min,
ReplyDeletePls explain how you got the value in table 3 using the other datasheet pls because SUMIF structure is: =SUMIF(Range, Criteria, Sum Range). Where is your criteria? Thanks.
Again to plot the actual progress chart, what should be plotted against time from the procurement actual progress calculation sheet. Thanks
Hello,
ReplyDeleteThis site is really great.
Pls explain to us hw you got table 3 thanks
ReplyDeletegreat post and i realy enjoyed it.
ReplyDeleteThanks for the useful information.
ReplyDeleteCould u please send me the procurement excel sheet For updating
My id mohammedshohebc@gmail.com
HOW to prepare skyline of the pre-commissioning and commissioning in excel?
ReplyDelete