WBS Code Descriptions
E Electrical Construction
E.1 Plant Area
E.1.1 Building No
E.1.1.1 Substation Work and Feeder Cabling
E.1.1.1.1 Generator/substation work
E.1.1.1.1.1 Switchgear & Motor Control Centers Installation
E.1.1.1.1.2 Equipment & Panel Installation (Inter Posing Relay System)
E.1.1.1.1.3 New Panel installation
E.1.1.1.1.4 Panel Modification
E.1.1.1.1.5 Cable Tray Installation
E.1.1.1.1.7 Sand Filling
E.1.1.1.1.8 Indoor Cable Termination
E.1.1.1.2 Feeder Cabling
E.1.1.1.2.1 Cable laying
E.1.1.1.2.2 Cable Termination
E.1.1.1.2.3 Cable Splice
E.1.1.1.2.4 Sand Filling
E.1.1.1.2.5 Cable Tray Installation
E.1.1.1.2.6 Conduit Installation
E.1.2 Area Detail
E.1.2 .1 Power Wiring
E1.2.1.1 Power wiring for equipments
E.1.2.1.2 Cable laying
E.1.2.1.3 Cable Termination
E.1.2.1.4 Sand Filling
E.1.2.1.5 Cable tray Installation
E.1.2.2 Lighting Work
E.1.2.2.1 Panel Installation and Termination
E.1.2.2.2 Lighting Fixture Installation and Termination
E.1.2.2.3 Street Lighting Installation and Termination
E.1.2.2.4 Cable Laying
E.1.2.2.5 Cable Tray Installation
E.1.2.2.6 Junction Box Installation and Termination
E.1.2.2.7 Conduit Installation
E.1.2.3 Grounding Work
E.1.2.3.1 Grounding Electrode Installation with Well
E.1.2.3.2 Grounding Wire Installation and Connection
E.1.2.3.3 Cathodic Protection
E.1.2.4 Demolishing Work (if applicable)
The above WBS for electrical construction work can be represented as a hierarchical structure as shown in figure below.
See also Sample WBS for Mechanical Equipment Installation Work
The above WBS for electrical construction work can be represented as a hierarchical structure as shown in figure below.
See also Sample WBS for Mechanical Equipment Installation Work
Great post. Keep this good work of educating the planners.
ReplyDeleteRegards K.Suhail
really helpful... thanks